3A prayer was made to regularise the said
construction in terms of the Government policy.
Reliance is placed by the petitioner on the property
tax bill issued by the Navi Mumbai Municipal
Corporation. There is a reply filed by Shri
Pritamsingh Rajput, the Chief Controller of
Unauthorised Construction of CIDCO. It is pointed
out that on the basis of the site inspection
conducted on 21st October 2015, the impugned notice
was issued. At that time, photographs of the
structure were taken. A copy thereof has been
annexed to the affidavit. The record of assessment
is also annexed which shows that as on 1st April
2001, there was a residential structure admeasuring
39.06 sq meters. Now, there is a building
consisting of RCC ground plus three floors having
area of 122.745 sq meters. The photograph annexed
to the affidavit shows that the RCC work of ground
plus two floors is completed and RCC Construction of
third floor is in progress. The photograph is taken
on 21st October 2015. As far as policy of
regularization is concerned, affidavit clarifies
that the cut off date is 1st May 2007 and the
proposal submitted by the CIDCO to extend the cut
off date till 2012 is under consideration of the