Hariprasad Barai v. M/S. Conforce Engineers and Contractor
A compact analysis
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY APPELLATE SIDE CIVIL JURISDICTION
APPEAL FROM ORDER STAMP NO. 14748 OF 2016
Hariprasad Barai ....Appellant V/S
M/s. Conforce Engineers And Contractor ....Respondent
WITH
CIVIL APPLICATION IN AO STAMP NO. 14750 OF 2016 In
APPEAL FROM ORDER LODGING NO . 14748 OF 2016
Hariprasad Barai ....Applicant
V/S
M/s. Conforce Engineers And Contractor ....Respondent
CORAM : SMT. DR. SHALINI PHANSALKAR-JOSHI, J DATE : 6th October, 2016
P.C. :
Due to paucity of time the matter is adjourned, Ad-interim relief if any to continue till then. Stand over to 17/10/2016.
Parties & counsel
- appellant
Hariprasad Barai
- respondent
M/s. Conforce Engineers And Contractor
Coram
Shalini Phansalkar-Joshi
Case details
As recorded by the court registry
All orders in this case
2 orders share this CNR
- Order 1 — this page · Jitendra Shantilal Jain
- Order 2 · Jitendra Shantilal Jain
Similar cases
Judgements on the same questions, provisions and authorities, from every court