at Juhu were set out. A request was made to
approve the said proposal. The additional Municipal
Commissioner gave approval to the said proposal. The
date of commencement of the work was fixed and on
11th July 1985, the construction commenced. On 31st
July 1985 the Municipal Corporation stopped the
work. Thereafter, on 6th August 1985 according to
the case made out by the contractor, the Municipal
Engineer accepted the proposal for designing the
structure along with basement on IS 456-1978 and
also approved RCC design after obtaining sanction of
the Accounts Department and the Additional Municipal
Commissioner which was validated by the Education
Committee of the Municipal Corporation. On 24th
October 1985, the Municipal Corporation informed the
contractor to commence the work. Admittedly, on 7th
March 1986 a formal work order was issued by the
Municipal Corporation to the contractor calling upon
the contractor to deposit a sum of Rs.2,46,401/-. On
6th May 1986, the work was again ordered to be
stopped by the Municipal Corporation. The Contractor
claimed that on 3rd July 1986, a resolution was
passed by the General Body of the Municipal
Corporation bearing No. 203 by which it was resolved
to award the contract to the said contractor.
Accordingly, the contractor allegedly forwarded one
copy of the formal contract document duly singed to
the Municipal Corporation.