Bhartiya Vidya Bhavan (Bavla Compound) Co-Op Housing Society (Proposed) and 4 Others v. State of Maharashtra and 4 Others
Case brief
What is this about?
Cluster redevelopment on MHADA land was obstructed by a prior Government permission condition and cancellation of the NOC. The court held the condition unsupported by DCR 33(9), rejected the statutory and minimum-area objections, and allowed the petition challenging the letters and condition. MHADA received four weeks to comply; stay was refused.
What did the court decide?
Petition allowed in terms of prayer clause (a)(i) to (iv), quashing the challenged letters and condition No.13; MHADA granted four weeks for compliance.