and the Management of the defendant in which it was assured by the defendant that, either on completion of construction, conveyance in respect of the premises would be executed or the outstanding amount returned with interest or compensation in lieu of the proposed area of 5,000 sq.ft would be paid, which ever is higher. Then, at para-9, the plaintiff refers to the letter dated 20th December, 2011 sent to the defendant for return of the outstanding amount with interest. By the said notice, the plaintiff demanded payment of the principle amount of Rs.1,58,56,000/- and interest thereon of Rs.23,50,57,355/- @ 24% p.a. (yearly cumulative) with effect from 1st April, 1995. The actual claim made in the suit, however is for Rs.1,41,00,000/- towards the principle and Rs.96,69,896/- towards interest @ 24% p.a. At para-21 of the plaint, the plaintiff describes the suit claim as “loan amount advanced”. Therefore, the claim made in the suit is to be taken as “for payment of loan advanced” by the plaintiff to the defendant sometime in the year 1990.