Sasangi Engineering (Bombay) Pvt. Ltd. and Anr. v. Sah Sunil Kumar and Ors.
Case brief
What is this about?
This fourth-false finish judgment analysed the document's handling and observed that the application sought a stay of the operation and implementation of an impugned judgment and decree. The court noted that the First Appeal was already admitted and that existing ad-interim relief granted earlier was continued until today. Consequently, the court held that the applicant made out a case for allowin
What did the court decide?
The operation and implementation of the impugned judgment and decree dated 30.11.2012 passed by Bombay City Civil Court in S.C. Suit No. 3789 of 1995 was stayed till the hearing and final disposal of