Hubtown Ltd. and Anr. v. Municipal Corporation and 7 Ors.
Case brief
What is this about?
The High Court held that experts' certificates confirmed the property lies outside the CRZ buffer zone. Drawing on precedents, the court quashed MCZMA's objections regarding the absence of a new Coastal Zone Management Plan and directed the authority to grant clearance within four weeks.
What did the court decide?
Direction to MCZMA to issue clearance certificate within four weeks; direction to BMC to consider development application.