The Executive Engineer Krishna Khore Vikas Mahamandal M.I. Osmanabad v. Ashok Bhimaji Mahadik and Others
Case brief
What is this about?
The Bombay High Court at Aurangabad set aside the rejection of delay applications filed by the acquiring authority. The court condoned a delay of 117 days in filing appeals under Section 54 of the Land Acquisition Act, accepting official procedure as a valid reason.
What did the court decide?
Applications for condonation of delay were allowed; delay of 117 days was condoned in preferring the appeals under Section 54 of the Land Acquisition Act.