M/S.Saumya Builders Pvt.Ltd v. Union of India and Ors.
Case brief
What is this about?
The High Court held that a clarificatory amendment expanding the definition of 'built up area' applies to pending projects. However, relying on precedents preventing delay, the Court modified stop work notices to allow continuation of construction up to 20,000 sq. meters pending environmental and CRZ clearances, requiring the petitioner to file an undertaking.
What did the court decide?
Stop work notices modified to restrain construction only beyond 20,000 sq. meters; petitioner directed to file undertaking not to exceed limit and must obtain clearances thereafter.