power house in ICT contract No.2 to the petitioner. The work was completed by the petitioner on 31st March, 2000. The dispute arose between the parties during the execution of the work in respect of hidden expenses. The petitioner invoked arbitration clause. On 27th April, 1998, first arbitration proceedings started. The matter was referred to the arbitration. On 26th June, 2003, the Arbitral Tribunal made an award in favour of the petitioner awarding a sum of Rs.17,81,25,152/-. Being aggrieved by the said award, the State Government filed Arbitration Application No. 44 of 2003 on 22nd March, 2003 in the court of District Judge, Ratnagiri challenging the said award under section 34 of the Arbitration and Conciliation Act, 1996. By an order and judgment dated 29th June, 2006, the learned District Judge dealt with five objections which were raised by the Government by way of preliminary objections only and negatived each of such objection and rejected the said arbitration application. Being aggrieved by the said order and judgment dated 29th June, 2006, the State Government filed appeal (6 of 2007) under section 37 of the Arbitration and Conciliation Act, 1996 in this Court.