M/S. J. N. Construction, v. M/S. Shah Jagshi Jethabhai
Case brief
What is this about?
Held the appeal set aside the lower court's order quashing part of an arbitral award. The High Court restored the first claim as the arbitrator reasonably inferred payment applied to an earlier bill, but upheld the setting aside of the second claim for delay due to lack of evidence. Also corrected the error regarding applications of procedure codes.
What did the court decide?
The judgment setting aside the award on the first claim is set aside; the award for Rs.4,56,136.80 is affirmed with interest; the judgment setting aside the award on the second claim is affirmed.