Maharashtra State Road Development Corporation Ltd. , Mumbai v. M/S B. Seenaiah and Co. (Projects) Ltd. and 2 Ors.
Case brief
What is this about?
In this arbitration petition, the High Court modified an arbitral award by reducing the rate of interest from 15% to 9% p.a., while affirming the principal relief and rejection of the counter-claim, relying on the nature of the construction contract.
What did the court decide?
Impugned award modified to grant interest at 9% p.a. instead of 15% p.a.; rest of the award maintained; no order as to costs.