M/S. Nirmal Mutha Engineering Works Pvt.Ltd.and Ors. v. Krloskar Pneumatic Company Ltd.
Case brief
What is this about?
ndm FARAD CONTINUATION SHEET No. IN THE HIGH…
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
1
3 caf.3866.02
ndm
FARAD CONTINUATION SHEET No.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION
CIVIL APPLICATION NO. 3866 OF 2002
IN FIRST APPEAL NO. 1364 OF 2002
Office Notes, Office Memoranda of Coram, appearances, Court’s orders or directions and Registrar’s orders
Court’s or Judge’s orders
Mr. R.M.Haridas i/b Mr.P.N.Joshi for the Applicants.
P.C.
Heard the learned counsel appearing for the Applicant. If compliance is made by the Applicant with ad-interim order dated 23rd October, 2002, ad-interim relief will continue to operate as interim relief. If compliance has not been made with the adinterim order, the application will stand rejected. Application is disposed of.
Applicant
As recorded by the court registry