Hanamant G. Jadhav v. Union of India and 3 Ors.
Case brief
What is this about?
The High Court terminated the mandate of an existing Arbitral Tribunal for failure to act promptly. By consent of parties, the Court ordered the General Manager, Central Railway, to constitute a new Tribunal of three arbitrators within two weeks to adjudicate the claims and counter-claims from the stage of the last hearing of the earlier Tribunal.
What did the court decide?
Mandate of the existing Arbitral Tribunal terminated; General Manager directed to constitute a new Tribunal of three arbitrators within two weeks.