Union of India v. M/S.Jay Construction
Case brief
What is this about?
This court allowed an arbitration petition challenging an award that granted the respondent 'Extra overhead expenses' for a delayed and terminated railway construction contract. The judgment set aside the award to that extent, holding that it violated the contract terms as the contractor had already received full settlement.
What did the court decide?
Set aside the award regarding the claim for Extra overhead expenses (Claim No.3); maintain the rest of the award.