This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION
jmi
COMPANY APPLICATION NO.401 OF 2009
IN
COMPANY PETITION NO.926 OF 2008.
Narendra Kumar Sarawagi. ..Respondent/ Org. Petitioner. vs. M/s. Chetas Control Systems. ..Applicants/ Org. Respondents.
Mr. Ganavale, i/b. Sandeep Bhagwat, for Applicants/ Org. Respondents.
Mr. Rajeev Kumar Jain, i/b. Hina Shah, for Petitioner.
CORAM : S.J.KATHAWALLA, J. DATE : 3RD AUGUST 2009.
P.C.
On respondent-company depositing Bank guarantee of a
nationalised bank of Rs. 20 lacs. with the Prothonotary and Senior
Master within a period of 3 weeks from today, company application
is made absolute in terms of prayer clause (a).
company petition within one week from today. Petitioners shall file
2
their rejoinder within 2 weeks thereafter.
[ S.J.KATHAWALLA, J. ]
Narendra Kumar Sarawagi
M/s. Chetas Control Systems
S.J. Kathawalla
As recorded by the court registry