FPA-PMLA-1408/MUM/2016 of Shapoorji Pallonji & Co. Pvt. Ltd. v/s The Deputy Director, Directorate of Enforcement, Mumbai
Case brief
What is this about?
The Tribunal granted the appellant one final compliance period of two weeks to comply with an execution order. The respondent failed to comply by citing a challenge before the Bombay High Court.
What did the court decide?
Two-week compliance period granted. Otherwise, prayer for execution to be considered on next date.