FPA-PMLA-1588/ HYD/2016 of M/s Harish Infrastructure Pvt. Ltd. v/s The Joint Director Directorate of Enforcement, Hyderabad
Case brief
What is this about?
The Adjudicating Authority ordered a two-week extension for filing replies in connected proceedings regarding an appeal under the PMLA. Both parties failed to comply with a prior order, and the interim stay order was continued pending further development of pleadings. The matter was listed for May 2, 2017.
What did the court decide?
Extension of two weeks granted for filing replies; interim stay order continued; matter listed for May 2, 2017.