Appeal No. 59 of 2016 & Appeal No. 60 of 2016 of M/s Aravali Transmission Service Company Ltd. v. M/s Rajasthan Electricity Regulatory Commission & Ors.
Case brief
What is this about?
The Tribunal allowed appeals by licensees against a Regulatory Commission order regarding compensation for project delays. It held that initial regulatory rejections constituted a 'Change in Law' and 'Force Majeure' event, entitling the appellants to compensation for increased project costs and tax hikes. However, compensation for loss of revenue was rejected. The Tribunal directed the respondents to refund liquidated damages for delays caused by these regulatory events and remanded the matter for computation of specific compensation.
What did the court decide?
Respondents directed to refund liquidated damages with carrying costs. Awarded compensation for increased project costs and tax hikes with carrying costs. Compensation for loss of revenue rejected. Matter remanded to RERC to compute compensation.