Appeal No. 104 of 2019 of M/s. Swasti Power Engineering Ltd. v. Punjab State Electricity Regulatory Commission & Ors.
Case brief
What is this about?
The Appellate Tribunal for Electricity examined the validity of a termination notice and specific performance direction in a power purchase dispute. It held the notice invalid due to procedural default regarding force majeure notification. While affirming the force majeure rejection, the Tribunal set aside the declaration of the UPCL PPA as void and the specific performance order.
What did the court decide?
Affirmed the rejection of Force Majeure plea; set aside the declaration of the PPA with UPCL as void ab initio and the direction for specific performance under the PPA with PTC.