Apl No 194 of 2022 of Powergrid Southern Interconnector Transmission System Limited (Psitsl) v. Central Electricity Regulatory Commission & Ors.
Case brief
What is this about?
Appeal against CERC order rejecting PSITSL's claims of Force Majeure and Change in Law. Tribunal found farmers' agitation causing delay qualified as Force Majeure due to lack of control, holding Appellant entitled to 289-day extension. Relisted Commission to determine cost implications.
What did the court decide?
Appellant entitled to time extension of 289 days. Commission to pass fresh order on relief within two months.