Apl No 100 Of 2017 & Apl No 389 Of 2018 of Greenko Budhil Hydro Power Private Limited. v. Uttarakhand Electricity Regulatory Commission & Anr.
Case brief
What is this about?
Appeal Tribunal allowed the appellant generator's challenge to UERC's tariff order correcting Design Energy calculation and tie-line loss deductions, remanded capital cost disallowance matters. Another appellant’s appeal regarding NAPAF and design energy was dismissed for lack of merit.
What did the court decide?
Order dated 30.11.2016 set aside; Design Energy fixed at 280 MUs; Commission directed to re-calculate saleable energy deducting tie-line losses and re-determine capital cost (hard cost, soft cost, IDC