commissioning the instant asset; the Appellant had submitted that, as per the 2014 Tariff Regulations, the timeline for construction of a new 400/220 kV sub-station was 30 months against which normally 24 months are taken in many projects in case of urgency; the Ministry of Power, vide its letter dated 8.1.2015, had directed the Appellant to complete the transmission lines including the pooling station in a compressed time schedule to match it with the generation of RUMSL; the timeline for construction of solar park was about 12-15 months as discussed in the 38th meeting of the Standing Committee of Power system planning in WR; hence, the Appellant had squeezed all the construction activities, and had reduced the time line to 14 months to match the transmission scheme with the commission of generation, as discussed in above mentioned Standing Committee Meeting; the Chairperson of RUMSL and the Principal Secretary, New and Renewable Energy Department, Govt. of Madhya Pradesh, had informed, vide letter dated 9.12.2016, that the time line of the Generation Project had been revised and could be connected with the transmission system in October, 2017; an affidavit was filed by the Appellant on 5.3.2018 stating that the Executive Engineer, RUMSL, vide letter dated 3.10.2017, had requested for revision of the time line, for operationalisation of LTA and connectivity of Rewa Project, to February, 2018; and by the letter dated 28.2.2018, regarding the minutes on Grid Integration of RUMSL and related issues held at WRLDC, POSOCO,