“61.The Commission is of the view that the delay in processing and deciding on the request of the Petitioner dated 12.07.2019 by SECI and MNRE and communicating the decision by SECI prevented the Petitioner from performing the contract (PPA between PTC and the Petitioner) during the period from 12.07.2019 till 21.11.2019. As a nodal agency, it was the responsibility of SECI to initiate appropriate action as the project of the Petitioner was eligible for extension in SCoD in terms of the PPA read with the PSA. Had SECI taken diligent and prompt action as expected of it, based on this information submitted by the Petitioner vide letter dated 18.04.2019, the extension in SCoD in terms of the PPA could have been granted in time (possibly even before the date of extended SCoD of 13.06.2019) and the resultant delay could have been avoided, thereby giving the Petitioner certainty of time to implement the project. The Petitioner cannot be held responsible for any inaction during this period when SECI, on one hand, had already intimated that it has initiated the action as per MNRE Guidelines, Clause 3.17(B) of RfS and Article 4.6.2 of PPA and, on the other hand, MNRE and SECI were processing the case for the extension of SCoD of the project. The Petitioner could not have anticipated the decision of extension of SCoD from a retrospective date, and acted in the meanwhile.