A.No. 280 of 2021 & Ia No. 835 of 2021 of the Tata Power Company Limited - Transmission. v. Maharashtra Electricity Regulatory Commission & Ors.
Case brief
What is this about?
The appellate tribunal examined the validity of the MERC's decision to grant the Kudus-Aarey HVDC transmission license under Section 62 of the Electricity Act. Rejecting claims that the appellant had vested rights or that the process violated Section 15, the court upheld the appeal's dismissal, affirming that historicity justified the Regulated Tariff Mechanism and that Section 62 and 63 coexist without one overriding the other in case-to-case discretion.
What did the court decide?
The appeal and the pending application were dismissed, upholding the MERC's grant of the transmission license under Section 62.