A.No. 223 of 2019 & Ia No. 139 of 2022 of Torrent Power Limited. v. Gujarat Electricity Regulatory Commission.
Case brief
What is this about?
The Appellate Tribunal allowed the appeal after the parties agreed to remit the matter to the State Commission for reconsideration of methodology regarding carrying costs with an expedite direction.
What did the court decide?
Impugned order set aside; matter remitted to State Commission for reconsideration of carrying cost methodology.