“36. As per the above judgement, JSW Energy Ltd. had a conditional environmental clearance wherein environmental clearance mandated detailed study regarding the impact of the project, if any, on Alphanso mango and marine fisheries as recommended in the report of Dr. B.S. Konkan Krishi Vidyapith, whereas there was no such condition in environmental clearance granted to the Petitioner. Further, the present case is similar to the Gujarat Bid 01 PPA and Haryana PPAs, in terms of non-availability of environmental clearance(s) as on cut-off date, whereas JSW Energy Ltd had environmental clearance as on bid date with certain conditions stipulated therein . Thus, the environmental clearance granted to the Petitioner was not conditional and was independent of any specific study. Accordingly, in terms of the above decision of the Commission and order of APTEL, the case of JSW Energy Ltd., is distinguishable from the present case of the Petitioner. Therefore, the judgment of APTEL dated 21.1.2013cannot be made applicable to Gujarat Bid 01 PPAs. The need for installation of FGD has arisen on account of the 2015 MoEF&CC notification dated 7.12.2015 vide which the Ministry has notified stringent norms to be complied by the thermal power generating stations within two years. The Petitioner has achieved COD and has been supplying power to GUVNL till date without FGD. While there were no norms specified for NOx emission by Thermal Power generating stations as on cut-off date, the Nox norms as per MoEF&CC notification is 600 mg / Nm3 for unit size less than 500 MW…