A.No. 83 of 2017 of U.P.Ceramics & Potteries Ltd. v. Rajasthan Electricity Regulatory Commission & Ors.
Case brief
What is this about?
The Appellate Tribunal allowed the appeal against the State Commission's order declining payment for electricity supplied between April and June 2015. The Tribunal directed the Discom to pay the charges and late surcharge under the PPA.
What did the court decide?
Impugned order set aside; Discom directed to pay charges for April-June 2015 with late payment surcharge under Clause 8.2(ii) of PPA within one month.