A.No. 70 of 2017 of Dcm Shriram Limited. v. Rajasthan Electricity Regulatory Commission & Ors.
Case brief
What is this about?
An appeal against excess demand charges imposed after a belated curtailment order. The tribunal held the appellant could not have complied retrospectively despite receiving instructions hours before the required start time. Excess drawal was attributable to delays by grid operators, not the consumer. Penalty was waived.
What did the court decide?
Impugned order by Rajasthan Electricity Regulatory Commission set aside to the extent challenged. Penalty of Rs. 2,97,61,356/- remanded for refund or adjustment.