A.Nos. 322 & 333 of 2016 of M/s Ultratech Cement Ltd. & Anr. v. Karnataka Electricity Regulatory Commission & Anr.
Case brief
What is this about?
The Appellate Tribunal allowed appeals filed by M/s Ultratech Cement Ltd. and JSW Steel Ltd., holding that cogeneration plants utilizing waste heat or gas are not liable to comply with Renewable Purchase Obligation (RPO) under Section 86(1)(e) of the Electricity Act, 2003, as they must be treated at par with renewable sources for promotional purposes.
What did the court decide?
The impugned order dated 25.08.2016 passed by the Karnataka Electricity Regulatory Commission was set aside, and the appeals were allowed.