A.No. 332 of 2016 of Nuclear Power Corporation of India Limited. v. Central Electricity Regulatory Commission & Ors..
Case brief
What is this about?
The Appellate Tribunal for Electricity dismissed an appeal filed by NPCIL challenging a CERC order that held it liable to pay transmission charges. The Tribunal upheld the CERC order, ruling that NPCIL must bear the cost for delaying the project's full operation despite the lack of a direct contract, citing its regulatory powers.
What did the court decide?
The appeal was dismissed as devoid of merits; the impugned order dated 21.9.2016 passed by the Central Commission is upheld.