The Tribunal dismissed the appeal, upholding the State Commission's order. It held that the delay in commissioning the solar plant was due to the Discom's inaction in shifting electric poles, constituting an event of default under the PPA. Consequently, the Appellant could not impose liquidated damages or encash the Performance Bank Guarantee.
What did the court decide?
The Impugned Order dated 16.3.2016 passed by the State Commission was upheld.