Appeal No. 199 of 2012 of The South Indian Sugar Mills Association & Ors. v. Tamil Nadu Electricity Regulatory Commission & Ors.
Case brief
What is this about?
Appellate Tribunal for Electricity disposed of an appeal by several sugar mills against a tariff order for bagasse-based cogeneration plants. The Tribunal allowed the appeal in part, remanding issues on capital cost, fuel cost, incentives, and O&M charges to the State Commission for fresh determination, while dismissing challenges regarding consultative papers, promotional measures, and Plant Load
What did the court decide?
The appeal was allowed to the extent indicated; the matter was remanded to the State Commission for fresh determination of capital cost, fuel cost, incentives, and O&M charges within 180 days.