112 of 2012 of Tamil Nadu Generation and Distribution Corporation Ltd. v. 1. M/s. Penna Electricity Ltd. 2. Tamil Nadu Electricity Regulatory Commission
Case brief
What is this about?
The Appeal Tribunal held that an unapproved amended Power Purchase Agreement is not binding. The Commission correctly determined tariff under Section 62, relying on Central Commission Regulations, and directed fixed charges for open cycle power supplied as firm power.
What did the court decide?
The appeal filed by TANGEDCO was dismissed as devoid of merit; the order of the State Commission fixing fixed and variable charges was upheld.