Archana Exports v. the State of Andhra Pradesh
Case brief
What is this about?
The petitioner, Archana Exports, was awarded a contract for supply, delivery and installation of sandstone gazebos at Shilparamam, Vizianagaram and Visakhapatnam. Despite completion of work and finalization of bills, the respondents withheld payment of Rs. 36,89,246/-. Respondent No. 2 filed a counter-affidavit stating the bill was uploaded on the NIDHI portal and awaits fund clearance. The High Court disposed of the writ petition directing the respondents to release the due amount within three months, and held that any interest clause in the agreement is binding on both parties.
What did the court decide?
Direction to respondents to release Rs. 36,89,246/- within three months from receipt of order; any interest clause in agreement binding on parties.