K.Kesavaiah v. The Southern Power Distribution Company of Andhra
Case brief
What is this about?
The petitioner challenged the cancellation of a one-year contract for operation and maintenance of five 33/11 KV sub-stations in Rural Chittoor Division, alleging violation of natural justice. The respondents had cancelled the tender claiming the petitioner failed to pay IR arrears to its employees. The court noted the entire tender period (2016-2017) had already been completed due to an interim direction, rendering the main petition infructuous. The court also declined to implead the petitioner's employees, holding their disputed claims for unpaid arrears could not be adjudicated in this writ petition. The writ petition and all pending miscellaneous applications were closed without costs.
What did the court decide?
Writ petition closed as infructuous; impleadment applications (I.A. Nos. 3 & 4 of 2016) dismissed with liberty to employees to pursue remedies; all pending miscellaneous applications closed. No costs.