Jmj Bore Wells v. the State of Andhra Pradesh
Case brief
What is this about?
Andhra Pradesh HC Amaravati; Writ Petition No. 26912/2025 (decided 01.04.2026, Justice Subba Reddy Satti); Article 226 writ on unpaid contractor dues; money claim adjudicable in writ jurisdiction where dues admitted — reliance on Utkal Highways Engineers & Contractors v. CGM & Ors (2025 SCC OnLine SC 1400); alternative remedy objection rebutted post-exchange of affidavits; admitted/undisputed payment makes petition maintainable; NTR Sujala Padhakam; RWS&S; Kotauratla Mandal; Anakapalli; M Book 152/A/RWS/2005; TSr 106/2017-18 (07.02.2017); claimed Rs.2,17,028 vs payable-after-statutory-deductions Rs.2,12,820 confirmed via EE instructions dated 28.03.2026 and counsel endorsement; ordered release within two months; no costs; IA No.1/2025 under S.151 CPC; interest @24% p.a. sought but not awarded; pending miscellaneous petitions closed.
What did the court decide?
Direction to respondents to release Rs.2,12,820/- (Rupees Two Lakhs Twelve Thousand Eight Hundred and Twenty only) payable to the petitioner for the executed work, within two (02) months from the date of receipt of the copy of the order; no order as to costs; pending miscellaneous petitions, if any, closed.