Peddireddy Ramireddy v. the State of Andhra Pradesh
Case brief
What is this about?
The petitioner, a contractor, filed a writ petition under Article 226 seeking release of Rs.16,91,937/- admittedly due for construction of internal C.C. roads with side drains under the G.G.M.P. scheme. The State conceded the claim and the time required for payment. The court disposed of the petition directing the respondents to pay the admitted amount with interest within two months.
What did the court decide?
Respondents directed to release the admitted amount of Rs.16,91,937/- with interest as per entitlement within two months from the date of receipt of the order.