B Chandra Reddy v. the State of Andhra Pradesh
Case brief
What is this about?
The petitioner, a contractor, completed road improvement works under two agreements with the AP State Housing Corporation. The competent authority approved the final bills totaling Rs. 9,23,896, and the amounts were recorded in the M-Book, but payment was withheld pending fund release. The Standing Counsel for the Corporation admitted the dues and assured clearance upon fund availability. The court disposed of the writ petition at the admission stage, directing respondents to verify and release the admitted payments within six weeks.
What did the court decide?
Direction to respondents to verify and release admitted payments of Rs. 9,23,896 within six weeks from receipt of order copy.