The petitioner executed WMM and DBM repair works under a work order dated 22.04.2025 and agreement dated 26.04.2025 for the Prime Minister's program. Despite admission of dues by respondents, payment was delayed. The court disposed of the writ petition directing payment of Rs. 4,49,058.18 within three months, noting prior precedent that non-payment of admitted dues is arbitrary.
What did the court decide?
Respondents directed to pay Rs. 4,49,058.18 to the petitioner within three months from receipt of the order; any applicable interest clause in the agreement/work order binding on both parties.