Gounda Abdul Hameed v. The State of Andhra Pradesh
Case brief
What is this about?
The petitioner, a contractor, sought a writ of mandamus to compel government authorities to release payment of Rs. 25,27,458/- for maintenance and repair works completed at a Social Welfare Girls Hostel in Nandyal District under a 2025 agreement. The respondents did not dispute the completion of works or the admitted bill amount but cited paucity of funds for non-payment. The High Court directed the respondents to verify and release the due payments expeditiously, preferably within eight weeks, and disposed of the writ petition.
What did the court decide?
Directed respondents to verify and release the admitted contract bill of Rs. 25,27,458/- expeditiously, preferably within eight weeks.