Nasbabu Constructions Private Limited v. the State of Andhra Pradesh
Case brief
What is this about?
The petitioner construction company completed irrigation works under Agreement No. 77SE/2018-19 but the respondent authorities withheld payment of Rs. 8,58,07,865/- plus GST. The Executive Engineer admitted the work was executed satisfactorily and the amount was payable, but bills were pending due to objections from accounts officials. The High Court held that non-payment of admitted dues is arbitrary and a writ petition lies, directing payment of the admitted amount within two months.
What did the court decide?
Directed respondent authorities to pay the admitted/net amount to the petitioner company within two months from receipt of the order.