Margani Rama Chandra Rao v. The State of Andhra Pradesh
Case brief
What is this about?
Keywords: writ of mandamus; non-release of admitted final bill; contractor dues; payment within six weeks; GGMP; M-Book No.136A/2023-24; Upgradation of CC Road at Ambedkar Nagar 2nd Street, 13th Division; Rajahmundry Municipal Corporation; Executive Engineer; Pay and Accounts Officer, Dowalaiswaram; State of Andhra Pradesh MAUD and Finance; Articles 14, 21, 226; Section 151 CPC; I.A. No.1 of 2026; W.P. No.17533/2026; Justice Harinath.N; Andhra Pradesh High Court at Amaravati; decided 09.07.2026; disposed at admission stage.
What did the court decide?
Respondents directed to verify and release the payments due and payable to the petitioner as expeditiously as possible, preferably within six (06) weeks from receipt of a copy of the order; no order as to costs; pending miscellaneous petitions closed. ¶38