Right of Way (RoW) compensation for 400 KV D/C transmission lines; 10% versus 30% of land value; Ministry of Power guidelines dated 14.06.2024 and 21.03.2025; CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Regulations, 2022; Article 226 petition; Articles 14, 19, 21, 300-A; Collector and District Magistrate Anathapuramu proceedings Rc.No.G1/188/2025 dated 11.11.2025; Adani Renewable Energy Forty Two Ltd; APTRANSCO; Anantapur II REZ Transmission Limited; Yellanur, Putlur, Tadipatri Mandals; Tahasildar Tadipatri meetings 15.04.2026/20.05.2026/25.05.2026; writ petition disposed with direction to pay remaining four petitioners on par within four weeks; no costs; liberty reserved.
What did the court decide?
Direction to the concerned respondents to pay RoW compensation to the remaining four petitioners on par with the other petitioners within four weeks from receipt of the order; no order as to costs; liberty reserved to the petitioners to approach the appropriate forum for any other proceedings; miscellaneous petitions, if any, stand closed.