M/S Suma Sree Constructions v. the State of Andhra Pradesh
Case brief
What is this about?
Contractor payment dues; release of Rs.8,01,118/- for works executed; Tribal Welfare Department Andhra Pradesh; NABARD Tranche-XXII sanction; Writ of Mandamus Article 226; Articles 14, 19, 21, 300-A; Section 151 CPC interim payment application; direction to pay within 8 weeks; disposed without costs; single-judge bench Kiranmayee Mandava, J.; non-reportable.
What did the court decide?
Direction to the respondents to release the amounts due to the petitioner (Rs.8,01,118/-) within eight (08) weeks from the date of receipt of the order; no order as to costs; pending miscellaneous applications closed. ¶39