Psr Constructions v. the State of Ap
Case brief
What is this about?
Andhra Pradesh High Court, Amaravati; W.P.No.6638 of 2025; Justice V.Sujatha; decided 16.09.2025. Contractor PSR Constructions (counsel Venkat Sailendra G) sought release of admitted irrigation works dues under Agreement No.SE/2022-23 dated 02-07-2022, CFMS Bill Token No.2024-1534610, claiming non-payment arbitrary and demanding 18% p.a. interest. State (GP for Irrigation and CAD; GP for Finance and Planning) admitted net bill of Rs.2,57,07,914 (gross Rs.2,68,74,946.40 minus Rs.11,67,032 deductions), submitted via CFMS Bill No.2025-639662, held up on Nidhi Portal fund clearance. Court disposed the writ directing payment within six months, interest per subsisting contract clause, relying on W.P.No.10038 of 2021 (05.10.2021) and batch.
What did the court decide?
Writ petition disposed of by directing the respondents to release the admitted payments as expeditiously as possible, preferably within six (06) months from receipt of a copy of the order; interest payable only per any subsisting clause in the agreement/work order, binding on both parties; no costs imposed; miscellaneous petitions, if any, pending in the writ petition to stand closed.