G. Sridhar Gopala Krishna v. The Government of Andhra Pradesh
Case brief
What is this about?
Mandamus for payment of contractor's final bills; six irrigation/drainage works agreements of 2022-23 with the Executive Engineer, Drainage Division, Repalle (6th respondent); non-payment despite Quality Control Certificates; State plea of budget non-release; admitted amounts directed to be released within six months; interest confined to any subsisting contract/work-order clause; Articles 226, 14 and 19(1)(g) of the Constitution of India; Sections 15 and 16 of the MSME Act, 2006 invoked in the prayer; reliance on W.P.No.10038 of 2021 and batch (judgment dated 05.10.2021); Andhra Pradesh High Court at Amaravati; Smt Justice V. Sujatha; 06.10.2025; Writ Petition No. 4996 of 2024; disposed.
What did the court decide?
Direction to the respondents to release the five Quality Control Certificate amounts (Rs.13,38,345/-, Rs.15,76,557/-, Rs.24,62,646/-, Rs.12,95,712/- and Rs.29,01,267/-) to the petitioner within six (6) months from receipt of a copy of the order; interest only per any subsisting clause in the agreement/work order; no order as to costs; pending Miscellaneous Petitions, if any, closed.