Anaparthi Satyanarayana v. The State of Andhra Pradesh
Case brief
What is this about?
Delayed payment of land acquisition compensation; statutory interest under Section 80, Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - 9% per annum for first year from taking possession, 15% per annum thereafter on unpaid compensation; possession date disputed (21.12.2017 vs 06.07.2018); compensation Rs. 36,09,361/- paid on 26.09.2022 for Ac. 1.14 cents in Sy.No.193/1A, Pochavaram Village, Tallapudi Mandal, East Godavari District; Chinthalapudi Lift Irrigation Scheme; endorsement LDS No. 307/2021/A1 dated 03.11.2022 by Special Deputy Collector (LA), Polavaram Irrigation Project Right Main Canal (Unit-I), Kovvur refusing interest; writ of mandamus under Article 226; direction to compute and deposit interest within six weeks; no costs; parties: Anaparthi Satyanarayana v. State of Andhra Pradesh, District Collector East Godavari, Special Deputy Collector (LA); counsel: I. Koti Reddy Idamakanti; decided 05.08.2025.