Crr Constructions v. the State of Andhra Pradesh
Case brief
What is this about?
Contractor payment writ; mandamus-style time-bound direction (eight weeks) to respondents 2 and 3 to verify and release approved final bills of Rs.44,40,295/- for six completed municipal works; non-payment pleaded due to lack of funds; completion of work undisputed. Parties: Crr Constructions v. The State of Andhra Pradesh and Others. Bench: Justice Harinath.N. Court: High Court of Andhra Pradesh at Amaravati. Keywords: payment of bills, contractor dues, lack of funds, municipal corporation, agreement Nos. 38/2023-24, 320/JTOI/2023-24, 35/20224, 132/2023-24, 286/JTO-I/2023-24, 68/2023-24.
What did the court decide?
Direction to respondents 2 and 3 to verify and release the payments due to the petitioner within eight weeks; writ petition disposed of with no costs; pending miscellaneous petitions closed. ¶39