Sudhakara Infratech Pvt. Ltd. v. The State of Andhra Pradesh
Case brief
What is this about?
Sudhakara Infratech Pvt Ltd v State of Andhra Pradesh and others, W.P.No.2891/2025 (APHC010050252025), High Court of A.P. at Amaravati, Harinath.N, J, 08.09.2025. Contractor-payment mandamus: release of Rs.2,23,98,412/- (+ claimed 24% p.a. interest) for completed Strom Water Drainage Scheme AMRUTH-SAAP(16-20), Agreement No.3/AMRUT/2018-19, Tirupathi Municipal Corporation; final bills approved in M-Books but unpaid since 2023; direction to respondent Nos.2 and 3 to pay within six weeks; Article 226 read with Articles 14, 19, 21; Section 151 CPC interim-application petition; writ petition disposed, no costs, miscellaneous applications closed.
What did the court decide?
Direction to respondent Nos.2 and 3 to release the payments due payable to the petitioner within six weeks from receipt of the order; no order as to costs. ¶38